Home Forums PSM1 Exam Questions and Awnsers Who is responsible for monitoring the progress of work during a Sprint?

  • This topic is empty.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #26563
    Scrum Revolution
    Keymaster

    Who is responsible for monitoring the progress of work during a Sprint?

     

    A. Project Manager

    B. Developers

    C. Product Owner

    D. Scrum Master

     

    Correct Answer: B

    The Developers are responsible for monitoring the progress of work during a sprint

Viewing 1 post (of 1 total)
  • You must be logged in to reply to this topic.