Home › Forums › PSM1 Exam Questions and Awnsers › Who is responsible for monitoring the progress of work during a Sprint? This topic is empty. Viewing 1 post (of 1 total) Author Posts July 18, 2023 at 12:49 pm #26613 Scrum RevolutionKeymaster Who is responsible for monitoring the progress of work during a Sprint? A. Project Manager B. Developers C. Product Owner D. Scrum Master Correct Answer: B The Developers are responsible for monitoring the progress of work during a sprint Author Posts Viewing 1 post (of 1 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In