    When does the Scrum Team hold the Sprint Retrospective?

     

    A. At the end of each Sprint

    B. At the beginning of each Sprint

    C. Every month

    D. Only when the Product Owner requests it

     

    Correct Answer: A

    The Sprint Retrospective is held at the end of each Sprint. It is a dedicated time for the Scrum Team to inspect their processes and interactions and create a plan for improvements in the next Sprint