    During the Sprint Review, who presents the work done by the Scrum Team?

     

    A. The Product Owner

    B. The Scrum Master

    C. The Development Team

    D. The stakeholders

     

    Correct Answer: C

    During the Sprint Review, the Development Team presents the work they have completed during the sprint. They showcase the potentially releasable Increment and receive feedback from stakeholders