During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
A. When the Product Owner identifies new work
B. As soon as possible after they are identified
C. When the Scrum Master has time to enter them
D.During the Daily Scrum after the Development Team approves them
Correct Answer: B
New work or Product Backlog Items that are in Sprint that are further decomposed into smaller work items should be added to the Sprint backlog as soon as they are identified. This way the Development team can keep track of all the work that has to be done in Sprint