Home Forums PSM1 Exam Questions and Awnsers The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

  • This topic is empty.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #27429
    Scrum Revolution
    Keymaster

    The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

     

    A. Opportunities to Inspect and Adapt the Sprint Backlog are lost

    B. Impediments are raised and resolved more slowly

    C. The Product Owner cannot accurately report progress to the stakeholders

    D. Too much work is spent updating the Srum Board before the meeting

    E.The Scrum Master loses the ability to update the Gantt chart properly

    F. The Sprint plan may become inaccurate

     

    Correct Answer: A,B,F

    The Daily Scrum is a daily event because it allows for impediments to be raised early, it is also an inspect and adapt opportunity because every day the Development Team can see the problems the other members encounter, this way they are able to help each other. Not doing this could cause the Sprint plan to become inaccurate because the Developers could lose sight of what everyone is working on and what might be hindering progress

     

    Want to learn more about Scrum Events? Read our Blogpost ! https://scrumrevolution.com/the-basics-scrum-events/