A Scrum Master is essentially the same thing as a traditional PM (Project Manager)
A. True
B. False
Correct Answer: B
Scrum Masters can be project managers, and project managers can be Scrum masters, but they’re not the same thing. A Scrum Master is a role on a Scrum team, whereas a project manager refers to the professional leading virtually any type of project. And while a Scrum Master’s primary focus is leading a team and an organisation to follow Scrum principles, managing progress and keeping everyone motivated a project manager is occupied with the project