During Sprint Planning, every task must be estimated so the Developers know they have the capacity to complete them in the Sprint
A. True
B. False
Correct Answer: B
The goal of the Sprint Planning is to have enough work that is refined and clear to all to start the Sprint. It is not necessary to have every task already estimated
Posted : 25/02/2024 3:08 pm