During the Sprint Review, who presents the work done by the Scrum Team?

1 Posts
1 Users
0 Reactions
167 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

During the Sprint Review, who presents the work done by the Scrum Team?

A. The Product Owner
B. The Scrum Master
C. The Development Team
D. The stakeholders

Correct Answer: C

During the Sprint Review, the Development Team presents the work they have completed during the sprint. They showcase the potentially releasable Increment and receive feedback from stakeholders

 