During the Sprint Review, who presents the work done by the Scrum Team?
A. The Product Owner
B. The Scrum Master
C. The Development Team
D. The stakeholders
Correct Answer: C
During the Sprint Review, the Development Team presents the work they have completed during the sprint. They showcase the potentially releasable Increment and receive feedback from stakeholders