Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?

1 Posts
1 Users
0 Reactions
51 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?

A. Teach the Product Owner to work with the lead developers on ordering the Product Backlog in a way to avoid too much technical and development overlap during a Sprint
B. Teach them that it is their responsibility to work with the other teams to create an integrated Increment
C. Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint
D. Visit the five teams each day to inspect that their Sprint Backlogs are aligned

Correct Answer: B

The Scrum Master is there to facilitate Scrum and help guide the Teams towards self organisation, in this case it is the Scrum Masters job to teach the teams how to work together towards and integrated Increment.

 