How is management external to the Scrum Team involved in the Daily Scrum?

A. The Scrum Master speaks on their behalf
B. Managers are not required at the Daily Scrum
C. Management gives an update at the start of each Daily Scrum
D. The Product Owner represents their opinions

Correct Answer: B

The Product Owner represents the opinions of the Stakeholders and management. However only the Development Team is supposed to be present at the Daily Scrum. The Product Owner and Scrum Master can join if they are picking up Development tasks.

 