How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

1 Posts
1 Users
0 Reactions
62 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

A. A proportional amount of time on analysis, design, programming, testing, and documentation
B. As much as it can fit into the Sprint
C. Any remaining work will be transferred to a subsequent Sprint
D. All development work and at least some testing
E. As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of “Done”

Correct Answer: E

In Scrum all Product Backlog items must meet the Definition of "Done" in order to be completed before the end of the Sprint

 
Posted : 25/02/2024 3:13 pm