Notifications
Clear all
PSM1 Questions with Answers
1
Posts
1
Users
0
Reactions
67
Views
Topic starter
If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?
A. The evolution of the cost spent on the project
B. When all work will be completed to the Scrum Team can be released for other work
C. When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team
D. When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added
Correct Answer: C
The trend line of the Burn-down Chart shows the evolution of work completed and the work remaining untill the end of the sprint
Posted : 25/02/2024 3:10 pm