In Scrum, what is the primary purpose of the Increment at the end of a Sprint?
A. To demonstrate the product to stakeholders for feedback
B. To have a potentially releasable version of the product
C. To provide evidence of work done during the Sprint
D. To have a backup of the product in case of failure
Correct Answer: B
The primary purpose of the Increment at the end of a Sprint is to have a potentially releasable version of the product. The Increment should meet the Definition of Done and be in a condition that it could be released to customers if the Product Owner decides to do so