The Product Owner should actively participate in the Daily Scrum to monitor the progress of the Development Team
A. True
B. False
Correct Answer: B
The Daily Scrum is a time-boxed event for the Development Team to synchronize and plan their work. The Product Owner may attend but should not actively participate unless invited by the Development Team. The Daily Scrum is primarily for the Development Team to inspect progress and plan for the day