The Scrum Master is responsible for resolving all impediments that the Development Team encounters during the Sprint
A. True
B. False
Correct Answer: B
While the Scrum Master plays a crucial role in facilitating the resolution of impediments, the entire Scrum Team, including the Product Owner and the Development Team, is responsible for identifying and addressing impediments. The Scrum Master helps to remove organizational or process impediments that are beyond the Development Team's control