The Scrum Team is responsible for selecting the Product Backlog items they can complete during the Sprint

A. True
B. False

Correct Answer: A

During Sprint Planning, the Scrum Team, including the Product Owner and the Development Team, collaboratively decides which Product Backlog items to select for the Sprint. The Development Team is responsible for determining how much work they can commit to completing based on their capacity

 