Notifications
Clear all
PSM1 Questions with Answers
1
Posts
1
Users
0
Reactions
123
Views
Topic starter
The Sprint Planning event consists of two parts: the first part to define the Sprint Goal, and the second part to plan the Sprint Backlog
A. True
B. False
Correct Answer: A
The Sprint Planning event is time-boxed and consists of two parts. In the first part, the Scrum Team defines the Sprint Goal, and in the second part, the Development Team collaboratively plans the work necessary to achieve the Sprint Goal and create the Sprint Backlog
Posted : 25/02/2024 3:21 pm