The Sprint Planning event consists of two parts: the first part to define the Sprint Goal, and the second part to plan the Sprint Backlog

1 Posts
1 Users
0 Reactions
123 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

The Sprint Planning event consists of two parts: the first part to define the Sprint Goal, and the second part to plan the Sprint Backlog

A. True
B. False

Correct Answer: A

The Sprint Planning event is time-boxed and consists of two parts. In the first part, the Scrum Team defines the Sprint Goal, and in the second part, the Development Team collaboratively plans the work necessary to achieve the Sprint Goal and create the Sprint Backlog

 