The Sprint Planning event is comprised of 2 parts and the Product Owner is not needed at the 2nd part

1 Posts
1 Users
0 Reactions
53 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

The Sprint Planning event is comprised of 2 parts and the Product Owner is not needed at the 2nd part

A. True
B. False

Correct Answer: B

In past versions of the Scrum Guide, the Sprint Planning event was described as having 2 parts. This is no longer true

 