Three Scrum Teams are working on the same Product. It is recommended that the teams must merge their code before the Sprint ends

A. True
B. False

Correct Answer: A

The purpose of a Sprint is to create a useful Increment. If the code from multiple teams has not been merged a useful and potentially releasable Increment cant be created. Regardless of how many teams work on the same Product, their code should be merged

 