Forum

What is the key con...
 
Notifications
Clear all

What is the key concern when multiple Development Teams are working from the same Product Backlog?

1 Posts
1 Users
0 Reactions
57 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

What is the key concern when multiple Development Teams are working from the same Product Backlog?

A. Minimizing dependencies between teams
B. Clear definition of requirements
C. Meeting original scope projections
D. Making sure there's enough work for everyone on every team
E. Maximizing velocity

Correct Answer: A

In this situation a Scrum Master should focus on decreasing dependencies between the Development Teams. This will decrease complexity

 
Posted : 25/02/2024 2:53 pm
Share: