Forum

What type of test s...
 
Notifications
Clear all

What type of test should be done during the Sprint?

1 Posts
1 Users
0 Reactions
108 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

What type of test should be done during the Sprint?

A. Every type of test
B. All tests except for user acceptance tests
C. Unit tests
D. All tests except for integration tests

Correct Answer: A

An Increment should be "Done" and usable by the end of the Sprint. This also means that all kind of tests have to be done

 
Posted : 25/02/2024 2:48 pm
Share:
×

Upgrade Now!

Want to access premium quizzes? Sign up now and unlock all of our amazing features!