What type of test should be done during the Sprint?

A. Every type of test
B. All tests except for user acceptance tests
C. Unit tests
D. All tests except for integration tests

Correct Answer: A

An Increment should be "Done" and usable by the end of the Sprint. This also means that all kind of tests have to be done

 