Which of the following is mandatory in Scrum?
A. Burn-down charts
B. Test-Driven Development
C. Planning Poker
D. Progress measurement
E. Face-to-face communications
Correct Answer: D
Progress measurement is essential when working with Scrum, Scrum is meant to facilitate incremental releases while remaining agile. If you cant track the progress you also cant stay agile