Which of the following is required by Scrum?
A. Sprint Retrospective
B. Members must be stand up at the Daily Scrum
C. Sprint Burn-down Chart
D. Release planning
E. All of the above
Correct Answer: A
Of the options offered, only the Sprint Retrospective is required