Who can change the Sprint Backlog during a Sprint?
A. The Scrum Master
B. The Product owner
C. Stakeholders
D. The Developers
Correct Answer: D
Only the Developers can change the Sprint Backlog during a Sprint, the Product Owner can change the Product Backlog.