Forum

If burndown charts ...
 
Notifications
Clear all

If burndown charts are used to visualize progress, what does a trendline through a release burndown chart indicate?

1 Posts
1 Users
0 Reactions
172 Views
(@roy-slotboom_pewjck65)
Posts: 261
Member Admin
Topic starter
 

If burndown charts are used to visualize progress, what does a trendline through a release burndown chart indicate?

A. When all work will be completed so the Scrum Team can start work on a new Product Backlog
B. When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added
C. When the work remaining is projected to be completed if nothing changes on the Product Backlog or Development Team
D. The evolution of the return of investment on the project

Correct Answer: C

The trend line on the burndown chart indicates the work remaining based on the previous period. If nothing changes to the Backlog the trendline shows the work remaining for the sprint.

 
Posted : 25/02/2024 6:13 pm
Share: