A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what “Done” means. (Choose two)
A. All work the Development Team is willing to do
B. Ready for integration
C. No work left from the definition of “Done”
D. Whatever the Product Owner defines as quality
E. All work to create software that is ready to be released to end users
Correct Answer: C,E
In Scrum work is “Done” when it meets the Definition of “Done”. This is to stop confusion, if not everyone has the same Definition of what “Done” means unfinished work might be released to end users