A Development Team member wants to use a new technology in the current Sprint to increase the product’s performance significantly. The team has no prior experience with this technology. What should the Development Team do?
A. Proceed with using the new technology, as it might provide a competitive advantage
B. Include the new technology in the current Sprint and seek help from external experts
C. Conduct a Spike in the current Sprint to assess the feasibility and risks of using the new technology
D. Wait until the next Sprint to introduce the new technology to ensure a smoother integration.
Correct Answer: C
A Spike is a time-boxed activity that allows the Development Team to explore new technologies, approaches, or solutions to gain the knowledge needed to address a specific problem or make a decision. Conducting a Spike in the current Sprint will help the team assess the feasibility and potential risks associated with using the new technology without committing to it fully