A Scrum Team uses 2 week Sprints and time boxes their Sprint Planning. How long should their Sprint Planning be?
A. 2 hours
B. 4 hours
C. 6 hours
D. 8 hours
Correct Answer: B
Sprint Planning is timeboxed to a maximum of 8 hours for a one-month Sprint. For shorter Sprints, the event is usually shorter