    A software development company is making a software for an Airport Terminal. 7 Scrum Teams are working together on this huge software project. For such a complicated software project each team should: (Select two best answers)

     

    A. Maintain one Product Backlog and coordinate with only one Product Owner

    B. Maintain a shared “Definition of Done”

    C. Maintain one Scrum Master

    D. Maintain a separate Product Backlog and Product Owner based on specific functions

    E. Maintain a separate Scrum Master to manage the added complications

     

    Correct Answer: A,B

    Every Product should have one Product Backlog with one Product Owner. Every Product should also have only one Definition of “Done”. Adding more Backlogs, Product Owners or Definitions of “Done” would add unwanted complexity. But, every team should have a Scrum Master