    An Increment is..

     

    A. All work that was carried out in the Sprint

    B. All work that has happened up to the current point in time

    C. All work completed up to now, where there are no bugs present

    D. The sum of the Done work during a Sprint, plus the work Done in earlier Sprints

     

    Correct Answer: D

    An Increment is the sum of the Done work during a Sprint, plus the work Done in earlier Sprints