    As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)

     

    A. Recruit additional Development Team members before the work can begin

    B. The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress

    C. Cancel the Sprint

    D. Remove or change selected Product Backlog items

    E. The Development Team works overtime during this Sprint

     

    Correct Answer: B,D

    If the workload is greater than the Development team can handle they can remove Items on the Sprint Backlog since the Development team is self-organized. This should however always happen with the knowledge of the Product Owner so the Product Owner can inform the Stakeholders.