    Choose two responsibilities of a self-organising Development Team. (Choose two)

     

    A. Reorder the Product Backlog

    B. Pull Product Backlog items for the Sprint

    C. Do the work planned in the Sprint Backlog

    D. Increase velocity

    E. Report daily progress to stakeholders

     

    Correct Answer: B,C

    The Development Team is responsible for completing the work planned in the Sprint Backlog. The Sprint Backlog is made up of items the Development Team pulls from the Product Backlog