    Does the composition of Developers remain constant?

     

    A. Always

    B. Can change during the Sprint

    C. Can’t change during the Sprint but can change for different Sprints

     

    Correct Answer: C

    According to the Scrum Guide the composition of the Development Team can change for different Sprints to accomodate required skill sets to convert the Backlog items into “Done” Increments