    During a Sprint, a Developer determines that the Scrum Team will not be able to complete the items in their forecast. Who should be present to review and adjust the Product Backlog items selected?

     

    A. The Product Owner and all stakeholders

    B. The Scrum Master, the project manager, and the Developers

    C. The Developers

    D. The Product Owner and the Developers

     

    Correct Answer: D

    If Product Backlog items in sprint (the Sprint Backlog) cant be completed they should be moved back to the Product Backlog, this should always happen together with the Product Owner since the Product Owner is responsible for the Product Backlog and its ordering.