    During the Daily Scrum, the Development Team identifies an impediment that they cannot resolve on their own. What should they do?

     

    A. Ask the Scrum Master to resolve the impediment immediately

    B. Raise the impediment to the stakeholders for resolution

    C. Use the time after the Daily Scrum to address the impediment as a team

    D. Escalate the impediment to the Product Owner for resolution

     

    Correct Answer: C

    During the Daily Scrum, the Development Team identifies impediments, and they are encouraged to use the time after the Daily Scrum to collaboratively address any impediments they cannot resolve on their own. The Scrum Master may facilitate the resolution process, but it is the Development Team’s responsibility to address impediments