    During the Sprint Retrospective, the Scrum Master notices that the Development Team is focusing only on negative aspects of their performance. What action should the Scrum Master take to address this issue?

     

    A. Encourage the team to focus on positive aspects as well to balance the discussion

    B. Facilitate a discussion on individual team member performance and contributions

    C. Assign action items to individual team members to address their weaknesses

    D. Extend the duration of the Sprint Retrospective to allow more time for discussion

     

    Correct Answer: A

    The Sprint Retrospective is a valuable opportunity for the Scrum Team to inspect and adapt their processes. The Scrum Master should encourage the team to balance the discussion by also focusing on positive aspects and successful practices, in addition to identifying areas for improvement