During the Sprint, the Product Owner changes the priority of a high-priority item, affecting the Sprint Goal. What should the Development Team do?
A. Refuse to accept the change, as it will disrupt the Sprint’s focus and progress
B. Re-plan the Sprint with the new priority and inform the stakeholders of the change
C. Continue working on the original priority, and discuss the change during the next Sprint Planning
D. Collaborate with the Product Owner to understand the reasons for the change and adjust the Sprint Goal accordingly
Correct Answer: D
The Sprint Goal provides overall direction and focus for the Sprint. If the Product Owner changes the priority of a high-priority item, it may impact the Sprint Goal. In such a situation, the Development Team should collaborate with the Product Owner to understand the reasons for the change and, if necessary, adjust the Sprint Goal to reflect the new priority