    For the purpose of transparency, when does Scrum say a valuable and useful increment must be available? (Choose the best answer)

     

    A. After the Acceptance Testing phase

    B. Before the release Sprint

    C. Every 3 Sprints

    D. At the end of every Sprint

    E. When the Product Owner asks to create one

     

    Correct Answer: D

    According to Scrum, at least one usable Increment should be produced during each Sprint