    In Scrum, what is the primary purpose of the Increment at the end of a Sprint?

     

    A. To demonstrate the product to stakeholders for feedback

    B. To have a potentially releasable version of the product

    C. To provide evidence of work done during the Sprint

    D. To have a backup of the product in case of failure

     

    Correct Answer: B

    The primary purpose of the Increment at the end of a Sprint is to have a potentially releasable version of the product. The Increment should meet the Definition of Done and be in a condition that it could be released to customers if the Product Owner decides to do so