    In Scrum, who is responsible for facilitating the Scrum events?

     

    A. The Scrum Master

    B. The Product Owner

    C. The Development Team

    D. The stakeholders

     

    Correct Answer: A

    The Scrum Master is responsible for facilitating the Scrum events, such as the Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. They ensure that these events are effective, time-boxed, and that all participants understand their purpose and goals

     

    Want to learn more about Scrum Events? Read our Blogpost ! https://scrumrevolution.com/the-basics-scrum-events/