    Product Backlog refinement is..

     

    A. A Scrum Event

    B. The concerns of the Product Owner

    C. An ongoing process in which the Product Owner and the Developers collaborate

    D. Carried out once per Sprint

     

    Correct Answer: C

    Product Backlog refinement is an ongoing process in which the Product Owner and the Developers collaborate

     