    The Length of a Sprint should be?

     

    A. Short enough to keep the business risk acceptable to the Product Owner

    B. Short enough to be able to synchronize the development work with other business events

    C. No more than one calendar month

    D. All of the above

     

    Correct Answer: D

    Sprints are limited to one calendar month. When determining the sprint length, the wishes of the organization should also be considered. In a very high paced organization, a shorter sprint might be desired