Home Forums PSM1 Exam Questions and Awnsers The result of the Sprint Review is..

  • This topic is empty.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #26769
    Scrum Revolution
    Keymaster

    The result of the Sprint Review is..

     

    A. Incomplete Product Backlog items have been reviewed and returned to the top of the Product Backlog

    B. The Increment has been demonstrated to Stakeholders

    C. Acceptance of all Product Backlog Items

    D. A revised Product Backlog that defines the probable Product Backlog items for the next Sprint

     

    Correct Answer: D

    The Sprint Review is meant to create an Inspect and Adapt opportunity for the Scrum team by showing the Stakeholders whats been “Done” and getting feedback. The result of this should be a revised Backlog for the next Sprint

Viewing 1 post (of 1 total)
  • You must be logged in to reply to this topic.