    The Scrum framework is purposefully incomplete. It only defines the parts required to implement Scrum theory

     

    A. True

    B. False

     

    Correct Answers: A

    The Scrum Framework is incomplete on purpose. It only defines the parts required to implement Scrum Theory becasue it should fit every Organization or solution