    The Scrum Team has just started a new project and is unsure about the initial estimates for Product Backlog items. How should they handle this situation during Sprint Planning?

     

    A.The Scrum Master should provide initial estimates to guide the team

    B. The team should use historical data from previous projects for estimation

    C. The Product Owner should prioritize the Product Backlog items based on complexity

    D. The Development Team should collaboratively estimate based on their best knowledge

     

    Correct Answer: D

    During Sprint Planning, the Development Team should collaboratively estimate the effort required for the Product Backlog items based on their best knowledge and expertise. Estimates should not be provided by the Scrum Master (A) or the Product Owner (C) but rather be a team effort based on the team’s understanding and experience