    The Sprint Planning event is comprised of 2 parts and the Product Owner is not needed at the 2nd part

     

    A. True

    B. False

     

    Correct Answer: B

    In past versions of the Scrum Guide, the Sprint Planning event was described as having 2 parts. This is no longer true

     