    What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?

     

    A. There are no such activities, the next Sprint immediately follows the current Sprint

    B. Refine the Product Backlog

    C. Work with the Quality Assurance departments on the Increment of the current Sprint

    D. Update the project plan with stakeholders

     

    Correct Answer: A

    There are no such activities, the next Sprint immediately follows the current Sprint