    What is the difference between “Definition of Done” and “Acceptance Criteria” for a Product Backlog item?

     

    A. Definition of Done is a detailed description for a Product Backlog item to be complete, while Acceptance Criteria are the quality standards that the item must meet

    B. Definition of Done is used in the Product Backlog refinement, while Acceptance Criteria are used during Sprint Planning

    C. Definition of Done is applied at the end of the Sprint to verify if the work is complete, while Acceptance Criteria are used during Sprint Review

    D. Definition of Done is shared among all Product Backlog items, while Acceptance Criteria are specific to each item

     

    Correct Answer: A

    The Definition of Done (DoD) represents the criteria that must be met for a Product Backlog item to be considered complete, including quality standards, testing, and any other necessary activities. Acceptance Criteria, on the other hand, are specific conditions that a Product Backlog item must satisfy to be accepted by the Product Owner as done so they can be released

     

    Want to learn more about the Definition of “Done”? Read our Blogpost! https://scrumrevolution.com/whats-the-deal-with-done/