    What is the key concern when multiple Development Teams are working from the same Product Backlog?

     

    A. Minimizing dependencies between teams

    B. Clear definition of requirements

    C. Meeting original scope projections

    D. Making sure there’s enough work for everyone on every team

    E. Maximizing velocity

    Correct Answer: A

    In this situation a Scrum Master should focus on decreasing dependencies between the Development Teams. This will decrease complexity